articles

Castle Shannon Parks Plus Plan Updates

September 6, 2023

Group 1 of the Parks Plus Plan consists of the library, Prospect Park, and Myrtle Park, and all of these projects are nearing completion!

Myrtle and Prospect Parks received some much-needed updates and new play equipment, and the library's new entranceway and outdoor reading areas look lovely!

Group 2, Lower Hamilton Park, has been fully excavated and is in the process of removing debris to make room for the new pavilion and

facilities. The projected end date for Lower Hamilton is mid-May. 

Group 3, Upper and Mid Hamilton Park, is currently ahead of schedule and is projected for a 2024 construction season with an opening to the public in early 2025.